| Address |
P.O. Unchahar, Dist. Rai Bareilly, Uttar Pradesh - 229406 |
| Telephone |
(STD-05311) - 211-2620 |
| Fax |
221065 |
| Email |
|
| Approved Capacity |
1050 MW |
| Installed Capacity |
Stage I & II : 840 MW (2 x 210 + 2 x 210 MW)
Stage III : 210 MW (1 x 210 MW)
|
| Location |
Raibareli, Uttar Pradesh |
| Coal Source |
North Karanpura |
| Water Source |
Sarda Sahayak Canal |
| Beneficiary States |
Uttar Pradesh, Haryana, Himachal
Pradesh, J&K, Punjab, Rajasthan,
Chandigarh, Delhi, Uttranchal
|
| Approved Cost |
Stage I & II : Rs.2337.09 Crores Stage III : Rs. 938.61 Crores |
| Unit Sizes |
5x210 MW |
| Units Commissioned |
Unit I : 210 MW November 1988
Unit II : 210 MW March 1989
Unit III : 210 MW January 1999 Unit IV : 210 MW October 1999
Unit V : 210 MW Sepetmeber 2006
|
| International Assistance (Stage II) |
ADB |
|


|