| Address: |
P.O.
Nabarun-742 236,Dist. Murshidabad,West Bengal
(STD-FKN-03485, KJT-03512) |
| Telephone: |
(STD-FKN-03485,
KJT-03512) KJT -224241
FKN - 252131 |
| Fax: |
KJT-26449 |
| Email
|
|
| Approved
Capacity |
2100
MW |
| Installed
Capacity |
1600
MW |
| Location |
Murshidabad,
West Bengal |
| Coal
Source |
Rajmahal
Coal Fields of ECL |
| Water
Source |
Farakka
Feeder Canal |
| Beneficiary
States |
West Bengal, Bihar,Jharkhand, Orissa, Sikkim, Assam, Tripura
and Damodar Valley Corporation.
|
| Approved
Investment |
Stage I: Rs.
730.93 Crore
Stage II: Rs.
2453.29 Crore |
| Unit
Sizes |
Stage
- I: 3x 200 MW
Stage -II: 2x 500 MW
Stage -III expansion of Farakkaa STPP is approved with the addition of one 500 MW unit.
|
| Units
Commissioned |
Unit
-I 200 MW January 1986
Unit -II 200 MW December 1986
Unit -III 200 MW August 1987
Unit -IV 500 MW September 1992
Unit -V 500 MW February 1994 |
| International
Assistance |
IBRD
KFW
Italian assistance, Banker's Trust co.
EXIM Bank, Japan, IDA |
| |
|

|